What this means for your building
- Check how people get out. An access-controlled door belongs on the compliance schedule under SS 3/2 when it has a security control and its failure could trap someone inside.
- Plan for the annual sign-off. An independent qualified person (IQP) issues Form 12A when all required procedures for the system have been completed over the previous 12 months. The owner uses it for the building warrant of fitness (BWoF).
- Before changing hardware, get the compliance schedule and approved fire plan. Identify the door, then check consent and schedule implications with the designer and council before ordering.
Does this door belong on the compliance schedule?
Stand on the side people use to leave. What happens if the reader is offline or the site switches to its after-hours setting while a cleaner is inside? Assess the whole opening, including any secondary lock. MBIE Compliance Schedule Handbook, SS 3/1 and SS 3/2.
| Door | What to check |
|---|---|
| Maglocked staff exit | Must the magnet release for someone to leave? If its failure could trap them, SS 3/2 applies. |
| Electric strike with a free inside lever | If the lever mechanically releases every fastening, even after hours, entry control alone may fall outside SS 3/2. A lever that only signals the controller still depends on electrical release. |
| Automatic shop entrance | Assess the operator under SS 3/1. If failure of a security lock could also trap someone, assess SS 3/2 as well. |
Choosing hardware for an existing door? Compare maglocks, electric strikes and other access control locks.
How should a maglocked exit release?
Everyday exit. A staff member might use a push-to-exit button or an exit sensor. Check that a wheelchair user can reach or trigger it and has time to pass through.
If the normal release fails, the industry code for manually opened escape doors held by an electrical lock calls for a separate, clearly identified emergency release at the door. A green break-glass or resettable unit is a familiar example. It releases the lock independently and keeps it released until reset. Association of Building Compliance guidance, sections 6.1–6.3 (PDF).
Ask the fire designer to record the required response to an alarm, loss of power and a door fault, including when backup power is available. Under C/AS2, an electromechanical fastening must unlock on power loss or malfunction, or provide a readily usable alternative that meets the locking-device requirements. Check keyless escape, any signage and any required panic hardware. C/AS2, sections 3.9.2 and 3.9.8 (PDF).
How much clear height is left below the maglock?
Where the approved fire design uses C/AS2, second edition, a doorway on or giving access to an escape route needs at least 1,955 mm clear height across the required width. Check the pathway and any greater clearance specified for your building. The escape route outside the doorway has separate headroom requirements. C/AS2, paragraph 3.2.1.1(b) (PDF).

Open the door to its required position. Measure from the finished floor or threshold to the lowest part of the fitted magnet or bracket within the required width. Allow for any new floor finish.
2,010 mm opening − 65 mm of hardware = 1,945 mm clear. That is 10 mm short on the C/AS2 pathway above. Change the mounting detail or select compatible hardware before ordering. Measure again after installation.
What changes for an automatic door?
SS 3/1 covers a door that opens without direct operation by a person when a failure could both injure and trap occupants. Where a security lock also meets SS 3/2, check both the operator and the lock. A device that holds a fire door open so it can close on alarm has a different function. Assess its interface under SS 3/3. MBIE guidance for specified systems SS 3/1–3/3.
A shopfront slider after closing. Ask the fire designer to mark its position on the escape route. C/AS2 restricts automatic doors and access control across routes leading into or within an exitway. In an open path or at a final exit, check the approved response to power loss or malfunction. It may require the doors to open and stay open at full required width, or allow people to push them outwards. The document also sets out an adjacent swing-door option for certain arrangements. C/AS2, section 3.9.6 and Figure 3.9.6.1 (PDF).
A powered swing door. Have the automatic-door and access-control contractors demonstrate the opening arc, safety detection and emergency operation together at handover.
What needs checking before the hardware changes?
Give council or the building consent authority the door number, approved plans and proposed change. If consented work changes a specified system, the schedule is amended through that consent. MBIE describes a separate Form 11 process for other amendments. Continue the existing inspections until the schedule is formally changed. MBIE guidance on amending a compliance schedule.
Before cutting a fire or smoke door, photograph the doorset label. Ask the supplier and designer for evidence that the proposed lock, frame preparation, closer and latching arrangement suit that assembly. A rating on the lock alone does not establish the rating of the altered doorset. NZS 4520 fire-resistant doorsets on Building CodeHub.
Who checks the doors, and how often?
The owner is responsible for arranging the work. The issued schedule gives the procedures, intervals and responsibilities for the building. Agree which routine checks site staff can carry out and which need an IQP accepted by the council for the relevant system.
- Access-controlled doors (SS 3/2). MBIE’s handbook gives daily checks while the building is in use for crowd occupancies, and for buildings where work may affect an access-controlled escape door. It gives monthly checks for other occupancies and six-monthly checks for all. Check that the route is clear and the door opens. Specialist checks cover the applicable release devices, alarm interface and backup supply.
- Automatic doors (SS 3/1). Where the nominated standard or document does not already set intervals, the handbook gives daily or monthly routine checks and annual technical checks. Include the operator, sensors and emergency operation as required by the schedule.
- Keep a door-by-door record. Log the date, person, result, defect, repair and retest. Keep inspection, maintenance and repair reports for at least two years and make routine check records available to the IQP.
If a door won’t release as designed, alert the building manager immediately. Arrange safe interim measures and repairs with the responsible professionals. MBIE handbook inspection tables (PDF). Owner’s inspection and maintenance duties.
Who signs Form 12 and Form 12A?
Form 12A — the IQP’s certificate. It confirms the inspection, maintenance and reporting procedures for the system(s) it covers were fully carried out over the preceding 12 months. One certificate can cover several doors. Keep the records traceable to each opening.
Form 12 — the owner’s BWoF. The owner or their agent supplies the BWoF and supporting Form 12As to council on the compliance schedule anniversary and displays a copy of the BWoF in the building. For a newly issued schedule, the council’s compliance schedule statement is displayed during the first 12 months. Download Forms 12 and 12A from MBIE. MBIE’s building owner guidance.
Missed a required check? Tell the IQP and council promptly. The IQP cannot certify full compliance for the affected system and period. Document what was missed, why it happened and the corrective action. A later service visit does not complete a missed inspection retrospectively. MBIE’s process for missed procedures.
What should you give the installer and IQP?
- Identify the opening. Give the door number, dimensions, direction of escape and any fire-door label. Include who is on site after hours.
- Record how it works. Cover entry, normal exit, emergency release, power failure and any alarm or automatic-operator interfaces. See how the reader, controller and door hardware work together.
- Agree the handover. Request a witnessed commissioning record, any revised schedule details, the next check date and the name of the person keeping the log.
Technical sources checked 24 November 2026. Use the approved fire design and issued compliance schedule for the individual building.
Planning a change to an access-controlled door?
Email NZTeco your door photos and site location. Show both faces of the door, the inside handle, the lock and the top of the frame. Include the existing hardware model if known, how people leave now and what you want to change.
NZTeco can help shortlist compatible equipment and coordinate the hardware details with your installer and IQP. For a call about the opening, contact the NZTeco team.